This guide is written for homeowners, architects and interior designers planning a new or renovated home, and it sits within our wider coverage of home automation in Hyderabad. It assumes you have already decided roughly what is being automated; if you have not, start with the electrical points checklist for home automation, which lists the twelve provisions to leave before plaster — the panel space being one of them.

What is actually inside the panel

People imagine a mysterious computer. In practice a home automation panel is a metal enclosure on a wall containing DIN-rail modules that do four jobs, plus the wiring that connects them.

What it isJobTypical DIN widthPlanning note
Protection — MCBs / RCBOBreaks each lighting and power circuit feeding the panel1–2 modules eachUsually lives in the main DB, but allow incomers and isolators inside the automation panel too.
Dimmer modulesDims lighting circuits — cove, downlights, pendants4–6 modules for 4–6 channelsThe main heat source. Never load every channel to its rated maximum.
Relay / switch modulesHard on-off for fans, geysers, non-dimmable loads, sockets4–6 modules for 8–12 channelsCheap per channel; over-provide rather than under-provide.
Curtain / motor modulesOpen, close and stop each motorised track2–4 modules per 2–4 tracksOne channel per track, not per room. Two tracks on one window is two channels.
Low-voltage driversConstant-voltage 24V supply for strip and cove lightingVaries; often mounted separatelyThe hottest item in the panel. Group them high or give them their own enclosure.
Controller / gatewayHolds the scenes, schedules and keypad logic; talks to the network2–4 modulesNeeds a wired network point at the panel, not Wi-Fi hope.
Power supply for the busFeeds keypads, sensors and the control bus2–4 modulesSize with headroom; adding keypads later adds load here.

Two observations follow from that table. First, the panel grows almost linearly with the number of controlled circuits, so the count of circuits — not the size of the house — drives everything. Second, roughly a third of the panel is heat-producing, which is why ventilation gets its own section below. If you are still deciding how many dimmable circuits you need and how to group them, how to plan dimmer channels and lighting loads works through watts per channel and minimum loads in detail.

Choosing the location: six rules and six places to refuse

The location is decided at drawing stage and is almost impossible to change afterwards, because every cable in the house is pulled towards it. Six rules we apply on every project:

  1. Central to the cable runs, not central to the floor plan. The aim is to minimise the longest run, typically keeping any circuit within about 25 to 30 metres of the panel. In a long apartment that often means the panel sits nearer the bedroom side than the geometric centre, because bedrooms carry more controlled points than a living room does.
  2. Permanently accessible without moving anything. A door that opens to at least 90 degrees, 700 to 900mm of clear standing space in front, and nothing stored against it. If reaching the panel means emptying a shelf of suitcases, it will not be serviced properly.
  3. Mounted at working height. Bottom of the enclosure around 1000 to 1200mm from finished floor level, top no higher than about 1800mm. Panels at ceiling level get worked on from a stool, badly.
  4. Dry, and with nothing wet above or behind. No water line, no drain stack, no washing machine point, no bathroom on the other face of that wall. Water finds panels.
  5. Close to the distribution board, but not inside it. Ideally the automation enclosure sits adjacent to the main DB so the sub-circuit feeds are short, while remaining a separate enclosure that can be opened without exposing the incoming supply.
  6. With a wired network point terminated inside. One Cat6 to the panel, from the router position, decided at the same time as the rest of the network. Our guide to planning Wi-Fi and home network for a smart home covers where the router and cable spine should sit.

The six locations we ask clients to change, in rough order of how often they come up:

One more practical note for apartments: check the handover drawing for the builder's concealed conduit runs before fixing the position, because the panel is far cheaper to move on paper than the conduits are to re-route. When to plan home automation during construction sets out the stage at which this conversation has to happen.

Sizing it: module counts, spare ways and enclosure dimensions

Size the panel by counting DIN modules for the design, then adding a quarter again. The table below is the starting envelope we use for Hyderabad homes before the actual circuit count is confirmed.

HomeTypical controlled circuitsModules for the designProvision to leavePractical enclosure
2BHK apartment14–22 lighting, 2–4 curtains, 3–5 keypads24–361 enclosure, 45–54 way~600 x 450 x 150mm, one location
3BHK apartment22–34 lighting, 4–7 curtains, 5–8 keypads36–541 enclosure, 63–72 way~800 x 600 x 200mm, one location
4BHK / large flat34–50 lighting, 6–10 curtains, 8–12 keypads54–721 large or 2 linked enclosures2 x 600 x 450mm side by side beats 1 huge box
Duplex / villa50–100+ across floors36–60 per floorOne enclosure per floor plus spareDistributed panels, linked by a cable spine

The 25 percent rule

Leave at least 25 percent of the rail width empty and one complete spare row after commissioning. This is the cheapest insurance in the entire project — a larger empty enclosure costs a few thousand rupees, while a full panel costs a new enclosure, a re-termination of every circuit and a day of downtime. In our experience the vast majority of homes add something within three years: a second curtain track, balcony or facade lighting, a camera circuit, a study that becomes a work-from-home room, or a terrace that gets covered.

Depth is the dimension people get wrong

Width and height are obvious; depth is what determines whether the panel can actually be wired neatly. Allow 150mm minimum, 200mm comfortable from wall face to inside of the door. Modules themselves are around 60 to 70mm deep, but the space behind and around them has to carry looms, ferrules, spare cable length and any driver bodies. A 100mm-deep enclosure forces cables to be pulled tight and cut short, which is exactly what makes a future change destructive.

Niche and civil provisions

If the panel sits in a recessed wall niche, ask the civil contractor for the opening at least 50mm larger than the enclosure on every side, with a lintel over it, a 100mm service gap behind for conduit entry, and no plumbing in that wall. Mark the niche on the plan at first fix, not when the modules arrive.

Heat, ventilation and why panels fail in year four

Most automation modules we deal with are rated for ambient temperatures up to roughly 50C, and like all electronics their working life shortens sharply as they approach that. A sealed plastic box in a closed cupboard on a May afternoon in Hyderabad can sit 10 to 15C above room temperature before you add the modules' own dissipation. That is how a panel that behaved perfectly for three years starts dropping a dimmer channel every summer.

Target an internal air temperature below about 40 to 45C at the worst hour of the year, and get there passively wherever you can:

Surge and earthing belong in the same conversation: the panel is where a surge event does the most expensive damage at once. Provisions for that are covered in electrical safety and power protection for a smart home.

Inside the panel: segregation, cable entry and dressing

A panel that is neat inside is not vanity. It is what makes a change in year five possible without re-tracing the house.

Labelling and documentation that still works in ten years

Assume that in eight years, a different electrician will open this panel, in a hurry, while a family stands behind them. Everything they need must be inside the door.

The panel is also the centre of the commissioning test — every channel proved, every scene run, every curtain limit set. Our home automation handover and testing checklist is the sign-off list we work through with the client at the panel door.

Eight panel mistakes and what each one costs

  1. No spare width. Cost: a new enclosure and a full re-termination when the family adds two curtains. Fix: 25 percent spare and one spare row, always.
  2. The panel behind joinery. Cost: carpentry on every service visit, and eventually a system nobody maintains. Fix: decide the location before the wardrobe drawing is frozen.
  3. Modules in the ceiling void. Cost: cutting a ceiling to reach a failed driver. Fix: everything serviceable lives in the panel; the ceiling holds fixtures only.
  4. An enclosure only 100mm deep. Cost: cables cut short, no service loop, a destructive change later. Fix: 150mm minimum, 200mm if there is any choice.
  5. Sealed box, no ventilation. Cost: summer dropouts from year three or four and a shortened module life. Fix: metal enclosure, vents low and high, spacing, and a ventilated cupboard.
  6. Data and mains bundled together. Cost: intermittent controller and bus faults that are miserable to diagnose. Fix: separate trunking, 50 to 75mm clearance, right-angle crossings.
  7. Handwritten or absent labels. Cost: every future fault becomes a tracing exercise billed by the hour. Fix: printed labels at both ends and a laminated schedule in the door.
  8. One giant panel for a three-floor villa. Cost: 40-metre cable runs, voltage drop and a single point of failure. Fix: one enclosure per floor, linked by a spine.

Most of these are decided in the first week of a project and paid for in the fifth year, which is precisely why they are worth an hour at drawing stage. If you are planning ongoing support as well, home automation maintenance and support in Hyderabad explains what happens after installation.

How Pert delivers it — a designed solution, not a DIY kit

Pert is a solutions company: we design and install. There is no version of a control panel that arrives in a box for a homeowner to mount, and we do not pretend otherwise. On every project our team fixes the panel location on the plan alongside the architect and the electrical contractor before first fix; counts the modules against the actual circuit schedule and then adds the spare capacity on top; specifies the enclosure size, depth, niche and ventilation for the civil contractor to build; sets out the internal layout with mains, low voltage and data segregated and the lighting drivers grouped where the heat can leave; terminates and ferrules every conductor with a service loop; proves every channel, curtain limit, keypad button and security circuit at commissioning; and hands over a labelled panel with a schedule inside the door and the as-built drawings as files. Then we are the people who open that door again when something needs changing — which is the real reason it is built to be opened.

If you are still choosing who should design and install this, best home automation companies in Hyderabad sets out what to check — including asking to see a photograph of a panel they handed over two years ago.

Planning a new home or renovation in Hyderabad and not sure where the panel should go? We will fix the location on your drawing, size the enclosure and niche for your civil contractor, and hand over a labelled panel with spare capacity built in. Request a consultation →

Frequently asked questions

Where should the home automation control panel be located in a house?

Somewhere dry, ventilated, central to the cable runs and permanently reachable without moving furniture — usually a dedicated utility or store cupboard, the wall beside the existing distribution board, or a purpose-made niche in a passage. Good locations have a door that opens fully, 700 to 900mm of clear standing space in front, no plumbing above or behind, and an ambient temperature that stays under about 40C. Avoid behind a fitted wardrobe, above a kitchen hob, inside a bathroom, in an unventilated shaft, on an external west wall, and anywhere a false ceiling has to be cut to reach it.

How big should a home automation panel be?

Count DIN modules, then add a quarter again. Roughly, a 2BHK lands at 24 to 36 modules, a 3BHK or 4BHK at 36 to 54, and a villa needs 36 to 60 per floor across two or three panels rather than one enormous one. Leave at least 25 percent spare width and one full spare row, because most families add a curtain, a facade line or a camera within three years. Physically, a 36 to 54 module enclosure is typically 600 to 800mm tall, 450 to 600mm wide and 150 to 200mm deep — and depth is the dimension people under-specify.

Does a home automation panel need ventilation or cooling?

Ventilation yes, air conditioning almost never. Keep internal air below about 40 to 45C, since modules are typically rated to around 50C and their life falls sharply near it. Use a metal enclosure rather than a sealed plastic one, filtered vents low and high so air convects through, 25 to 50mm between module rows, LED drivers grouped at the top or in their own enclosure, and channels derated to 70 to 80 percent of rating. Add a thermostatic filtered fan only where the cupboard itself runs hot or the module count is unusually dense.

Can a home automation panel be added to an existing home later?

Yes — the panel is rarely the hard part. The work is getting every lighting circuit, curtain point and keypad location to terminate at it, which is straightforward with accessible conduit or a false ceiling and expensive without. For retrofits we often plan two or three smaller distributed enclosures near existing junction points instead of one central panel, so cable runs stay short and walls stay closed. That call is made on site after tracing the existing conduit, never from a drawing alone.